Drainage Sluice no.-10 under polder-32 Construction work has been completed 77%. Photo was taken 04.03.2019
Drainage Sluice no.-11 under polder-32 Construction work has been completed 30%. Photo was taken 04.03.2019
Flushing Sluice no.-10 under polder-32 Construction work has been completed 12 %. Photo was taken 04.03.2019
Embankment work from chainage KM 1+750 to KM 2+750 under polder -32 . Re-SectioningWork is on going. Photo was taken 04.03.2019
Embankment work from chainage KM 21+000 to KM 21+300 under polder -32 . Re-SectioningWork is on going. Photo was taken 04.03.2019
The workers filled soil in synthetic sacks and raising the boat for dumping the Nalian Closure Dam. Photo was taken 04.03.2019
The workers filled soil in synthetic sacks and raising the boat for dumping the Nalian Closure Dam. Photo was taken 04.03.2019
" Water is spraying in CC Block at Pankhali CC Block manufacturing plant no.
01 under polder-32.This photo was taken on 27.11.2018."
Storge CC Block at Pankhali CC Block manufacturing plant no. 01 under polder-32.This photo was taken on 27.11.2018.
"Received compensation from BWDB but yet to remove their structures
from the alignment of embankment chainage: From 11+500 to 11+900 under polder-32.This photo was taken on 27.11.2018."
"Received compensation from BWDB but yet to remove their structures
from the alignment of embankment chainage: From 11+500 to 11+900 under polder-32.This photo was taken on 27.11.2018."
Drainage Sluice no. 11 under polder-32 Construction Work has been completed 3%.This photo was taken on 27.11.2018.
Drainage Sluice no. 11 under polder-32 Construction Work has been completed 3%.This photo was taken on 27.11.2018.
Drainage Sluice no. 10 under polder-32 Construction Work has been completed 30%.This photo was taken on 27.11.2018.
Drainage Sluice no. 10 under polder-32 Construction Work has been completed 30%.This photo was taken on 27.11.2018.
Sand filled synthetic bag dumping is going on in Nalian Closuer Dam under polder-32.This photo was taken on 27.11.2018.
Sand filled synthetic bag dumping is going on in Nalian Closuer Dam under polder-32.This photo was taken on 27.11.2018.
Sand filled synthetic bag dumping is going on in Nalian Closuer Dam under polder-32.This photo was taken on 27.11.2018.
Drainage Sluice no. 01 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Drainage Sluice no. 01 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Drainage Sluice no. 16 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Drainage Sluice no. 16 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Embankment work from chainage km 10+200 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Embankment work from chainage km 10+200 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Embankment work from chainage km 11+000 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
mbankment work from chainage km 11+100 under polder-35/1. Only tarfing and crest work has been remained.This photo was taken on 4 July 2018.
Embankment work from chainage km 11+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Embankment work from chainage km 11+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Embankment work from chainage km 11+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Embankment work from chainage km 19+000 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Embankment work from chainage km 19+000 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Emergency work from chainage KM 16+135 under polder-32.This photo was taken on 4 July 2018.
Emergency work from chainage KM 16+135 under polder-32.This photo was taken on 4 July 2018.
Emergency work from chainage KM 16+135 under polder-32.This photo was taken on 4 July 2018.
Emergency work from chainage KM 16+135 under polder-32.This photo was taken on 4 July 2018.
Slope protection work from chainage KM 9+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Slope protection work from chainage KM 9+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Slope protection work from chainage KM 9+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Slope protection work from chainage KM 9+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.
Earth/Embankment work of polder-32. Slop protection with tarfing work is being continued of chainage: 24+500 KM (Date: 30/05/2018)
Construction work is being constructed of Drainage Sluice no.01 under polder-32. (Date: 05/04/2018)
Drainage Sluice no. 02 under polder-32 construction Work has been completed about 90%. Connecting canal not yet to be done. (Date:05/04/2018)
Drainage Sluice no. 02 under polder-32 construction Work has been completed about 90%. Connecting canal not yet to be done. (Date:05/04/2018)
Construction work is being constructed of Drainage Sluice no.01 under polder-32. (Date: 05/04/2018)
Construction work is being constructed of Drainage Sluice no.01 under polder-32. (Date: 05/04/2018)
"Drainage Sluice No. - 11. Work Status: In Operation. Date of Image: 27/06/19 "
"Embankment work in embargo condition due to LAP/RAP issue. Chainage: Km 0-0.468. Date of Image: 27/06/19 "
"Embankment work in embargo condition due to LAP/RAP issue. Chainage: Km 0-0.468. Date of Image: 27/06/19 "
"Embankment work in embargo condition due to LAP/RAP issue. Chainage: Km 0-0.468. Date of Image: 27/06/19 "
"Drainage Sluice No. - 10. Work Status: 93%. Date of Image: 27/06/19 "
"Drainage Sluice No. - 09. Work Status: In Operation. Date of Image: 27/06/19 "
"Embankment work dropped because this road is under LGED. Chainage: Km 39.792-41.7. Date of Image: 27/06/19 "
" Dumping of Geo Bag ongoing in damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019"
"Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019 "
" Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019"
" Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019"
"Drainage Sluice no.-6 under polder-33 Construction work has been completed 24%. Photo was taken 06.03.2019"
"Flushing inlets no. -5 under polder-33 Construction work has been completed 58%. Photo was taken 06.03.2019"
"Flushing inlets no. -6 under polder-33 Construction work has been completed 63%. Photo was taken 06.03.2019"
"Flushing inlets no. -6 under polder-33 Construction work has been completed 23%. Photo was taken 06.03.2019"
"For Embankment work market is re-located from chainage km 0+00 to Km 0+500 under polder-33. Photo was taken 06.03.2019"
"Embankment work ( Re-Sectioning is ongoing) from chainage km 0+957 to Km 1+188 under polder-33 . Photo was taken 06.03.2019"
"Slope Protection Work from chainage km 0+800 to 1+200 under polder-33. Work has been completed. Photo was taken 06.03.2019"
Drainage Sluice no. 08 under polder-33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Embankment work from chainage km 28+510 - km 29+430 under polder-33 Construction Work has been completed fully in this section.This photo was taken on 3 July 2018.
Khal/Canal Excavation/Re-excavation work from chainage km 3+150 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Khal/Canal Excavation/Re-excavation work from chainage km 3+150 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Khal/Canal Excavation/Re-excavation work from chainage km 3+150 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Khal/Canal Excavation/Re-excavation work from chainage km 3+150 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Khal/Canal Excavation/Re-excavation work from chainage km 3+500 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Khal/Canal Excavation/Re-excavation work from chainage km 3+500 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Khal/Canal Excavation/Re-excavation work from chainage km 3+500 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Bank Protection work from chainage KM 21+500 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Bank Protection work from chainage KM 21+500 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Drainage Sluice no. 11 under polder-33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Embankment work from chainage km 41+500 under polder-33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Embankment work from chainage km 41+500 under polder-33 Construction Work has been completed fully.This photo was taken on 3 July 2018.
Storage CC Block at Mongla CC Block manufacturing plant under polder-33.This photo was taken on 28.11.2018.
Water is spraying in CC Block at Mongla CC Block manufacturing plant under polder-33.This photo was taken on 28.11.2018.
Drainage Sluice no. 10 under polder-33 Construction Work has been completed 0%.This photo was taken on 28.11.2018.
Drainage Sluice no. 10 under polder-33 Construction Work has been completed 0 %.This photo was taken on 28.11.2018.
Flushing Sluice no. 15 under polder-33 Construction Work has been completed 0 %.This photo was taken on 28.11.2018.
Flushing Sluice no. 15 under polder-33 Construction Work has been completed 0 %.This photo was taken on 28.11.2018.
Flushing Sluice no. 05 under polder-33 Construction Work has been completed 1%.This photo was taken on 28.11.2018.
Flushing Sluice no. 05 under polder-33 Construction Work has been completed 1%.This photo was taken on 28.11.2018.
Flushing Sluice no. 06 under polder-33 Construction Work has been completed 3%.This photo was taken on 28.11.2018.
Flushing Sluice no. 06 under polder-33 Construction Work has been completed 3%.This photo was taken on 28.11.2018.
Drainage Sluice no. 10 under polder-33 Construction Work has been completed 3%.This photo was taken on 28.11.2018.
Drainage Sluice no. 10 under polder-33 Construction Work has been completed 3%.This photo was taken on 28.11.2018.
"Slope protection work from chainage from KM 43+700 to 43+840 under polder-33 Construction Work has been completed 70%.This photo was taken on 28.11.2018."
"Slope protection work from chainage from KM 43+700 to 43+840 under polder-33 Construction Work has been completed 70%.This photo was taken on 28.11.2018."
"Received compensation from BWDB but yet to remove their structures from the alignment of embankment chainage: From 43+500 to 44+000 under polder-33.This photo was taken on 28.11.2018."
Dhopadi Khal(chainage 0+000 to 4+073 km) re-excavation works is being continued at polder-33. (Date: 30/05/2018)
Dhopadi Khal(chainage 0+000 to 4+073 km) re-excavation works is being continued at polder-33. (Date: 30/05/2018)
Drainage Sluice no. 09 under polder-33 construction Work has been completed about 90%. Connecting canal not yet to be done. (Date: 30/05/2018)
Drainage Sluice no. 09 under polder-33 construction Work has been completed about 90%. Connecting canal not yet to be done. (Date: 30/05/2018)
Construction work is being constructed of Drainage Sluice no. 07 under polder-33. (Date:30/05/2018)
Flushing Sluice No. - 22. Work Status: 96%. Date of Image: 28/06/19
Embankment work. Work Status: 95%. Date of Image: 28/06/19
Embankment work (CC Block dumping ongoing). Work Status: 80%. Date of Image: 28/06/19
Embankment work (CC Block dumping ongoing). Work Status: 80%. Date of Image: 28/06/19
Drainage Sluice No. - 04. Work Status: 100%. Date of Image: 28/06/19
Embankment work (Some existing houses and trees). Date of Image: 28/06/19
Embankment work (Some existing houses and trees). Date of Image: 28/06/19
Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
Emergency ring bundh work ongoing in damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
Emergency ring bundh work ongoing in damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
New crack on embankment due to Cyclone "Fani". Photo was taken on 07.05.2019
PD was discussing with local people about the new allignment of embankment. Photo was taken on 07.05.2019
PD was discussing with local people about the new allignment of embankment. Photo was taken on 07.05.2019
PD was discussing with local people about the new allignment of embankment. Photo was taken on 07.05.2019
Tafalbari CC Block Manufacturing plant. Photo was taken on 07.05.2019
Construction work is being constructed of Drainage Sluice no.04 under polder-35/1. (Date:27/05/2018)
Flushing Sluice no. 17 under polder-35/1 Construction Work has been completed about 90%. Connecting canal not yet to be done. This photo was taken on 2 July 2018.
Drainage Sluice no. 17 under polder-35/1 Construction Work has been completed about 90%. Connecting canal not yet to be done.This photo was taken on 2 July 2018.
Embankment work from chainage km 39+000 under polder-35/1. Crest work and turfing is remained in this section.This photo was taken on 2 July 2018.
Embankment work from chainage km 39+000 under polder-35/1. Crest work and turfing is remained in this section.This photo was taken on 2 July 2018.
Embankment work from chainage km 51+500 under polder-35/1. Crest work and turfing is remained in this section.This photo was taken on 2 July 2018.
Embankment work from chainage km 51+500 under polder-35/1. Work not yet started.This photo was taken on 2 July 2018.
Drainage Sluice no. 17 under polder-35/1 Construction Work has been completed about 90%. Connecting canal not yet to be done.This photo was taken on 2 July 2018.
Drainage Sluice no. 17 under polder-35/1 Construction Work has been completed about 90%. Connecting canal not yet to be done.This photo was taken on 2 July 2018.
"Flushing inlets no. -14 under polder-35/3 Construction work has been completed 78%. Photo was taken 07.03.2019"
Flushing Sluice no. 18 under polder-35/1 Construction Work has been completed 5%. . This photo was taken on 25.11.2018.
Flushing Sluice no. 18 under polder-35/1 Construction Work has been completed 5%. . This photo was taken on 25.11.2018.
Flushing Sluice no. 19 under polder-35/1 Construction Work has been completed 4%. This photo was taken on 25.11.2018.
Flushing Sluice no. 19 under polder-35/1 Construction Work has been completed 4%. This photo was taken on 25.11.2018.
Drainage Sluice no. 14 under polder-35/1 Construction Work has been completed 1%.This photo was taken on 25.11.2018.
Drainage Sluice no. 15 under polder-35/1 Construction Work has been completed 2%.This photo was taken on 25.11.2018.
Water is spraying in CC Block at tafalbari CC Block manufacturing plant under polder-35/1.This photo was taken on 25.11.2018.
Storge CC Block at tafalbari CC Block manufacturing plant under polder-35/1.This photo was taken on 25.11.2018.
The plastic piece found in the prepared CC Block are being canceled
Workers are neting brick chips using without PPE.This photo was taken on 25.11.2018.
Water is spraying in CC Block at Daratana CC Block manufacturing plant under polder-35/3.This photo was taken on 29.11.2018.
Storage CC Block at Daratana CC Block manufacturing plant under polder-35/3.This photo was taken on 29.11.2018.
Flushing Sluice no. 05 under polder-35/3 Construction Work has been completed 23%.This photo was taken on 29.11.2018.
Flushing Sluice no. 14 under polder-35/3 Construction Work has been completed 8%.This photo was taken on 29.11.2018.
"There is a Mosque situated in the chainage: From km 14+000 to km 14+500 in
Radhaballov under polder-35/3.This photo was taken on 29.11.2018."
"There is a Cemeterie situated in the chainage: From km 14+000 to km 14+500 in
Radhaballov under polder-35/3.This photo was taken on 29.11.2018."
"Many Electric Pole situated in the chainage: From km 14+000 to km 14+500 in
Radhaballov under polder-35/3.This photo was taken on 29.11.2018."
"There are still one house in the chainage: From km 30+000 to km 30+500 in
Khegraghat under polder-35/3.This photo was taken on 29.11.2018."
Earth/Embankment work of polder 35/3 has been completed from chainage : 16+892 to 19+620 . (Date:27/05/2018)
Construction work is being constructed of Drainage Sluice no.01 under polder-35/3. (Date:28/05/2018)
Drainage Sluice no. 1 under polder-35/3 . The structure was under construction and work progress is 77.7 %.This photo was taken on 5 July 2018.
Drainage Sluice no. 1 under polder-35/3 . The structure was under construction and work progress is 77.7 %.This photo was taken on 5 July 2018.
Drainage Sluice no. 1 under polder-35/3 . The structure was under construction and work progress is 77.7 %.This photo was taken on 5 July 2018.
Drainage Sluice no. 4 under polder-35/3 . The structure was under construction and work progress is 69 %.This photo was taken on 5 July 2018.
Drainage Sluice no. 4 under polder-35/3 . The structure was under construction and work progress is 69 %.This photo was taken on 5 July 2018.
Drainage Sluice no. 4 under polder-35/3 . The structure was under construction and work progress is 69 %.This photo was taken on 5 July 2018.
Old Drainage Sluice.This photo was taken on 5 July 2018.
Old Drainage Sluice.This photo was taken on 5 July 2018.
Flushing Sluice no. 13 under polder-35/3 Construction Work has been completed 100 %.This photo was taken on 5 July 2018.
Flushing Sluice no. 14 under polder-35/3 Construction Work has been completed 74 %.This photo was taken on 5 July 2018.
Embankment work from chainage km 4+500 under polder-35/3.Crest work and turfing is remained in this section.This photo was taken on 5 July 2018.
Embankment work from chainage km 4+500 under polder-35/3.Crest work and turfing is remained in this section.This photo was taken on 5 July 2018.
Embankment work from chainage km 5+500 under polder-35/3. Crest work and turfing is remained in this section.This photo was taken on 5 July 2018.
Embankment work from chainage km 5+500 under polder-35/3. Crest work and turfing is remained in this section.This photo was taken on 5 July 2018.
Embankment work from chainage km 6+200 under polder-35/3 Construction Work has been completed fully.This photo was taken on 5 July 2018.
Embankment work from chainage km 6+500 under polder-35/3 Construction Work has been completed fully.This photo was taken on 5 July 2018.
Embankment work from chainage km 7+500 under polder-35/3 Construction Work has been completed fully.This photo was taken on 5 July 2018.
Embankment work from chainage km 7+500 under polder-35/3 Construction Work has been completed fully.This photo was taken on 5 July 2018.
Embankment work from chainage km 7+500 under polder-35/3 Construction Work has been completed fully.This photo was taken on 5 July 2018.
Embankment work from chainage km 9+000 under polder-35/3 Work in progress.This photo was taken on 5 July 2018.
Embankment work from chainage km 9+000 under polder-35/3 Work in progress.This photo was taken on 5 July 2018.
Nadmulla CC Block Manufacturing plant. Per day CC Blocks production on an average-9500. Photo was taken 23.04.2019
River Bank Protection Work from chainage km 51.50 to km 54.00 under polder-39/2C. Dumping is on going. Photo was taken 23.04.2019
River Bank Protection Work from chainage km 51.50 to km 54.00 under polder-39/2C. CC Block placing only 600 m . Photo was taken 23.04.2019
River Bank Protection Work from chainage km 51.50 to km 54.00 under polder-39/2C. CC Block placing only 600 m. Photo was taken 23.04.2019
Drainage Sluice no.-7 under polder-39/2C. Construction work has been completed 42%. Photo was taken 27.03.2019
Drainage Sluice no.-12 under polder-39/2C. Construction work has been completed 84%. Photo was taken 27.03.2019
River Bank Protection Work from chainage km 51.50 to km 54.00 under polder-39/2C. Dumping is on going. Photo was taken 27.03.2019
Bank Protection work from chainage KM 51+500 to KM54+000 under polder -39/2C . Work is on going. Photo was taken 09.02.2019
Bank Protection work from chainage KM 51+500 to KM54+000 under polder -39/2C . Work is on going. Photo was taken 09.02.2019
Bank Protection work from chainage KM 51+500 to KM54+000 under polder -39/2C . Work is on going. Photo was taken 09.02.2019
CC block field.This photo was taken on 27.11.2018.
DS-1 under construction (97%).This photo was taken on 27.11.2018.
Drainage Sluice no.-12 under polder -39/2C. Construction work has been completed 70%. Remaining raling and third lift wing wall.This photo was taken on 22.07.2018
Drainage Sluice no.-12 under polder -39/2C. Construction work has been completed 70%. Remaining raling and third lift wing wall.This photo was taken on 22.07.2018
Drainage Sluice no.-12 under polder -39/2C. Construction work has been completed 70%. Remaining raling and third lift wing wall.This photo was taken on 22.07.2018
Drainage Sluice no.-12 under polder -39/2C. Construction work has been completed 70%. Remaining raling and third lift wing wall.This photo was taken on 22.07.2018
Drainage Sluice no.-12 under polder -39/2C. Construction work has been completed 70%. Remaining raling and third lift wing wall.This photo was taken on 22.07.2018
Drainage Sluice no.-2 under polder-40/2. Construction work has been completed 82%. Photo was taken 27.03.2019
Drainage Sluice no.-3 under polder-40/2. Construction work has been completed 12%. Photo was taken 27.03.2019
Drainage Sluice no.-5 under polder-40/2. Construction work has been completed 20%. Photo was taken 27.03.2019
Flushing inlets no. -4/1 under polder-40/2. Construction work has been completed 84%. Photo was taken 27.03.2019
Flushing inlets no. -9 under polder-40/2. Construction work has been completed 28%. Photo was taken 27.03.2020
Embankment work from chainage Km 4+150 to km 5.850 under polder -40/2 . Work has been completed. Photo was taken 27.03.2019
Embankment work from chainage Km 6+800 to km 7+500 under polder -40/2 . Re-Sectioning work is ongoing. Photo was taken 27.03.2019
Embankment work from chainage Km 9+000 to km 10+500 under polder -40/2 . Re-Sectioning work is ongoing. Photo was taken 27.03.2019
Embankment work from chainage Km 12+000 to km 12+400 under polder -40/2 . Re-Sectioning work is ongoing. Photo was taken 27.03.2019
Embankment work from chainage Km 12+000 to km 12+400 under polder -40/2 . Re-Sectioning work is ongoing. Photo was taken 27.03.2019
Flushing inlets no. -10 under polder-40/2. Construction work has been completed 58%. Photo was taken 27.03.2019
Gahorpur CC Blocks Manufacturing Plant . Photo was taken 08.02.2019
Gahorpur CC Blocks Manufacturing Plant . Photo was taken 08.02.2019
Embankment work from chainage km 4+150 to Km 6+650 under polder-40/2 work has been fully completed 2.40 km out of 34.40 km. Photo was taken 08.02.2019
Embankment work from chainage km 4+150 to Km 6+650 under polder-40/2 work has been fully completed 2.40 km out of 34.40 km. Photo was taken 08.02.2019
Flushing inlets no. 4/1 under polder-40/2 Construction work has been completed 84%. Photo was taken 08.02.2019
Drainage Sluice no.-2 under polder-40/2 Construction work has been completed 82%. Photo was taken 08.02.2019
Drainage Sluice no.-2 under polder-40/2 Construction work has been completed 82%. Photo was taken 08.02.2019
Embankment from chainage km 3+00 to Km 4+100 under polder-40/2 total free land is 11.5 km in different chainage . Photo was taken 08.02.2019
Embankment from chainage km 3+00 to Km 4+100 under polder-40/2 total free land is 11.5 km in different chainage . Photo was taken 08.02.2019
Embankment from chainage km 3+00 to Km 4+100 under polder-40/2 total free land is 11.5 km in different chainage . Photo was taken 08.02.2019
Embankment from chainage km 3+00 to Km 4+100 under polder-40/2 total free land is 11.5 km in different chainage . Photo was taken 08.02.2019
Drainage Sluice no.-4_5 under polder-40/2 Construction work has been completed 6 %. Photo was taken 08.02.2019
Drainage Sluice no.-4_5 under polder-40/2 Construction work has been completed 6 %. Photo was taken 08.02.2019
Flushing Sluice no.-9 under polder-40/2 Construction work has been completed 10 %. Photo was taken 08.02.2019
Flushing Sluice no.-9 under polder-40/2 Construction work has been completed 10 %. Photo was taken 08.02.2019
Flushing Sluice no.-10 under polder-40/2 Construction work has been completed 36 %. Photo was taken 08.02.2019
Flushing Sluice no.-10 under polder-40/2 Construction work has been completed 36 %. Photo was taken 08.02.2019
Flushing Sluice no. -4/1 under polder- 40/2. Construction Work has been completed about 90%. Remaining block placing and fit on gate .This photo was taken on 22.07.2018
Flushing Sluice no. -4/1 under polder- 40/2. Construction Work has been completed about 90%. Remaining block placing and fit on gate .This photo was taken on 22.07.2018
Flushing Sluice no. -4/1 under polder- 40/2. Construction Work has been completed about 90%. Remaining block placing and fit on gate .This photo was taken on 22.07.2018
Flushing Sluice no. -4/1 under polder- 40/2. Construction Work has been completed about 90%. Remaining block placing and fit on gate .This photo was taken on 22.07.2018
Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018
Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018
Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018
Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018
Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018
Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018
Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018
Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018
Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018
Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018
Embankment work from chainage km 5+950 -Km 6+650 under polder-40/2. Only turfing and crest work has been remained.This photo was taken on 22.07.2018
Embankment work from chainage km 5+950 -Km 6+650 under polder-40/2. Only turfing and crest work has been remained.This photo was taken on 22.07.2018
Embankment work from chainage km 5+950 -Km 6+650 under polder-40/2. Only turfing and crest work has been remained.This photo was taken on 22.07.2018
Embankment work from chainage km 5+950 -Km 6+650 under polder-40/2. Only turfing and crest work has been remained.This photo was taken on 22.07.2018
CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018
CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018
CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018
CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018
CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018
CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018
CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018
Meeting with LAP/RAP staff.This photo was taken on 26.11.2018.
DS-2 under construction (2%).This photo was taken on 26.11.2018.
Flushing Sluice no.-1 under polder-41/1. Construction work has been completed 72%. Photo was taken 25.04.2019
Flushing Sluice no.-3 under polder-41/1. Construction work has been completed 72%. Photo was taken 25.04.2019
Drainage Sluice no.-5 under polder-41/1. Construction work has been completed 72%. Photo was taken 25.04.2019
Drainage Sluice no.-7 under polder-41/1. Construction work has been completed 60%. Photo was taken 25.04.2019
Drainage Sluice no.-1 under polder-41/1. Construction work has been completed 18%. Photo was taken 28.03.2019
Drainage Sluice no.-5 under polder-41/1. Construction work has been completed 69%. Photo was taken 28.03.2019
Drainage Sluice no.-6 under polder-41/1. Construction work has been completed 55%. Photo was taken 28.03.2019
Drainage Sluice no.-7 under polder-41/1. Construction work has been completed 28%. Photo was taken 28.03.2019
Drainage Sluice no.-8 under polder-41/1. Construction work has been completed 70%. Photo was taken 28.03.2019
Drainage Sluice no.-9 under polder-41/1. Construction work has been completed 60%. Photo was taken 28.03.2019
Flushing inlets no. -1 under polder-41/1. Construction work has been completed 71%. Photo was taken 28.03.2019
Flushing inlets no. -3 under polder-41/1. Construction work has been completed 70%. Photo was taken 28.03.2019
Flushing inlets no. -8 under polder-41/1. Construction work has been completed 84%. Photo was taken 28.03.2019
Flushing inlets no. -9 under polder-41/1. Construction work has been completed 84%. Photo was taken 28.03.2019
Flushing inlets no. -15 under polder-41/1. Construction work has been completed 84%. Photo was taken 28.03.2019
Embankment work from chainage Km 6+100 to km 6+500 under polder -41/1 . Re-Sectioning work is ongoing. Photo was taken 28.03.2019
Embankment work from chainage Km 6+100 to km 6+500 under polder -41/1 . Re-Sectioning work is ongoing. Photo was taken 28.03.2019
Flushing Sluice no.-8 under polder-41/1 Construction work has been completed 84%. Photo was taken 07.02.2019
Drainge Sluice no.-5 under polder-41/1 Construction work has been completed 66%. Photo was taken 07.02.2019
Drainge Sluice no.-5 under polder-41/1 Construction work has been completed 66%. Photo was taken 07.02.2019
Flushing Sluice no. 9 under polder-41/1 Construction Work has been completed 84%. Photo was taken 07.02.2019
Flushing Sluice no. 9 under polder-41/1 Construction Work has been completed 84%. Photo was taken 07.02.2019
Embankment work from chainage km 6+100 to KM 13+000 under polder-41/1. Only tarfing and crest work has been remained. Photo was taken 07.02.2019
Embankment work from chainage km 6+100 to KM 13+000 under polder-41/1. Only tarfing and crest work has been remained. Photo was taken 07.02.2019
Drainge Sluice no.-7 under polder-41/1 Construction work has been completed 12%. Photo was taken 07.02.2019
Drainge Sluice no.-7 under polder-41/1 Construction work has been completed 12%. Photo was taken 07.02.2019
Drainge Sluice no.-8 under polder-41/1 Construction work has been completed 66%. Photo was taken 07.02.2019
Drainge Sluice no.-8 under polder-41/1 Construction work has been completed 66%. Photo was taken 07.02.2019
Drainge Sluice no.-6 under polder-41/1 Construction work has been completed 28%. Photo was taken 07.02.2019
Drainge Sluice no.-6 under polder-41/1 Construction work has been completed 28%. Photo was taken 07.02.2019
Flushing Sluice no. 15 under polder-41/1 Construction Work has been completed 84%. Photo was taken 07.02.2020
Flushing Sluice no. 15 under polder-41/1 Construction Work has been completed 84%. Photo was taken 07.02.2020
Gulbonia CC Blocks Manufacturing Plant under polder-41/1 . Photo was taken 07.02.2019
Gulbonia CC Blocks Manufacturing Plant under polder-41/1 . Photo was taken 07.02.2019
Drainge Sluice no.-9 under polder-41/1 Construction work has been completed 44%. Photo was taken 07.02.2019
Drainge Sluice no.-9 under polder-41/1 Construction work has been completed 44%. Photo was taken 07.02.2019
Progress Meeting with CSE.This photo was taken on 26.11.2018.
FS-3 under construction (2%).This photo was taken on 26.11.2018.
CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018
CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018
CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018
CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018
CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018
CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018
CC blocks manufactured at Gulbonia Casting Yard under polder-41/1. Per day CC block production rate is 250+ numbers.This photo was taken on 23.07.2018
CC blocks manufactured at Gulbonia Casting Yard under polder-41/1. Per day CC block production rate is 250+ numbers.This photo was taken on 23.07.2018
CC blocks manufactured at Gulbonia Casting Yard under polder-41/1. Per day CC block production rate is 250+ numbers.This photo was taken on 23.07.2018
CC blocks manufactured at Gulbonia Casting Yard under polder-41/1. Per day CC block production rate is 250+ numbers.This photo was taken on 23.07.2018
Flushing Sluice no. - 08 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018
Flushing Sluice no. - 08 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018
Flushing Sluice no. - 08 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018
Flushing Sluice no. - 08 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018
Flushing Sluice no. - 09 under polder- 41/1. Construction Work has been completed about 90%. Remaining raling and block setting .This photo was taken on 23.07.2018
Flushing Sluice no. - 09 under polder- 41/1. Construction Work has been completed about 90%. Remaining raling and block setting .This photo was taken on 23.07.2018
Flushing Sluice no. - 09 under polder- 41/1. Construction Work has been completed about 90%. Remaining raling and block setting .This photo was taken on 23.07.2018
Flushing Sluice no. - 09 under polder- 41/1. Construction Work has been completed about 90%. Remaining raling and block setting .This photo was taken on 23.07.2018
Flushing Sluice no. - 15 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018
Flushing Sluice no. - 15 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018
Flushing Sluice no. - 15 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018
Emergency work from chainage KM 5+050 - KM 5+225 beside the Burir char CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018
Emergency work from chainage KM 5+050 - KM 5+225 beside the Burir char CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018
Emergency work from chainage KM 5+050 - KM 5+225 beside the Burir char CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018
Emergency work from chainage KM 5+050 - KM 5+225 beside the Burir char CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018
Emergency work from chainage KM 13+650 - KM 13+250 beside the Gulbonia CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018
Emergency work from chainage KM 13+650 - KM 13+250 beside the Gulbonia CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018
Emergency work from chainage KM 13+650 - KM 13+250 beside the Gulbonia CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018
Emergency work from chainage KM 13+650 - KM 13+250 beside the Gulbonia CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018
Emergency work from chainage KM 13+650 - KM 13+250 beside the Gulbonia CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018
Drainge Sluice no.-2 under polder-47/2 Construction work has been completed 69%. Photo was taken 07.02.2019
Drainge Sluice no.-2 under polder-47/2 Construction work has been completed 69%. Photo was taken 07.02.2019
Flushing Sluice no.-1 under polder-47/2 Construction work has been completed 30%. Photo was taken 07.02.2019
Flushing Sluice no.-1 under polder-47/2 Construction work has been completed 30%. Photo was taken 07.02.2019
Drainge Sluice no.-1 under polder-47/2 Construction work has been completed 63%. Photo was taken 07.02.2019
Drainge Sluice no.-1 under polder-47/2 Construction work has been completed 63%. Photo was taken 07.02.2019
Embankment work from chainage km 0+000 to KM 2+000 under polder-47/2. Work has been completed 100%. Photo was taken 07.02.2019
Embankment work from chainage km 0+000 to KM 2+000 under polder-47/2. Work has been completed 100%. Photo was taken 07.02.2019
Gap of Embankment slope protection.This photo was taken on 25.11.2018.
FS-6 under construction (Progress 98%).This photo was taken on 25.11.2018.
DS-1 under construction (2%).This photo was taken on 25.11.2018.
CC blocks manufactured at Ramjanpur Casting Yard under polder-47/2. Per day CC block production rate is 150 numbers.This photo was taken on 25.07.2018
CC blocks manufactured at Ramjanpur Casting Yard under polder-47/2. Per day CC block production rate is 150 numbers.This photo was taken on 25.07.2018
CC blocks manufactured at Ramjanpur Casting Yard under polder-47/2. Per day CC block production rate is 150 numbers.This photo was taken on 25.07.2018
CC blocks manufactured at Ramjanpur Casting Yard under polder-47/2. Per day CC block production rate is 150 numbers.This photo was taken on 25.07.2018
CC blocks manufactured at Ramjanpur Casting Yard under polder-47/2. Per day CC block production rate is 150 numbers.This photo was taken on 25.07.2018
Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018
Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018
Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018
Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018
Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018
Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018
Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018
Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018
Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018
Embankment work from chainage km 5+500 - 2+575 under polder-47/2. Construction Work has been completed 100%.This photo was taken on 25.07.2018
Embankment work from chainage km 5+500 - 2+575 under polder-47/2. Construction Work has been completed 100%.This photo was taken on 25.07.2018
Embankment work from chainage km 5+500 - 2+575 under polder-47/2. Construction Work has been completed 100%.This photo was taken on 25.07.2018
Embankment work from chainage km 5+500 - 2+575 under polder-47/2. Construction Work has been completed 100%.This photo was taken on 25.07.2018
Flushing Sluice no. - 6 under polder- 47/2. Construction Work has been completed about 70%. Remaining raling and third lift wing wall.This photo was taken on 25.07.2018
Flushing Sluice no. - 6 under polder- 47/2. Construction Work has been completed about 70%. Remaining raling and third lift wing wall.This photo was taken on 25.07.2018
Flushing Sluice no. - 7 under polder- 47/2. Construction Work has been completed about 70%. Remaining raling and third lift wing wall.This photo was taken on 25.07.2018
Flushing Sluice no. - 7 under polder- 47/2. Construction Work has been completed about 70%. Remaining raling and third lift wing wall.This photo was taken on 25.07.2018
Slope Protection Work from chainage km 34.300 to km 34.550 under polder-48. Embankment work has been completed only CC Block placing has been remain. Photo was taken 24.04.2019
Drainage Sluice no.-1 under polder-48. Construction work has been completed 84%. Photo was taken 24.04.2019
Flushing Sluice no. -1 under polder-48. Construction work has been completed 70%. Photo was taken 24.04.2019
Flushing Sluice no. -3 under polder-48. Construction work has been completed 84%. Photo was taken 24.04.2019
Drainage Sluice no. -3/2 under polder-48. Construction work has been completed 74%. Photo was taken 24.04.2019
Drainage Sluice no. -3/4 under polder-48. Construction work has been completed 84%. Photo was taken 24.04.2019
Drainage Sluice no.-1 under polder-48. Construction work has been completed 74%. Photo was taken 29.03.2019
Flushing inlets no. -1 under polder-48. Construction work has been completed 50%. Photo was taken 29.03.2019
Slope Protection Work from chainage km 34+377 to 34+878. Dumping is on going. Photo was taken 07.02.2019
Slope Protection Work from chainage km 34+377 to 34+878. Dumping is on going. Photo was taken 07.02.2019
CC Blocks Manufacturing yYard No. -4 under-48. Photo was taken 07.02.2019
CC Blocks Manufacturing yYard No. -4 under-48. Photo was taken 07.02.2019
Flushing Sluice no. 1 under polder-48 Construction Work has been completed 30 %. Photo was taken 07.02.2019
Flushing Sluice no. 1 under polder-48 Construction Work has been completed 30 %. Photo was taken 07.02.2019
Drainge Sluice no.-1 under polder-48 Construction work has been completed 63%. Photo was taken 07.02.2019
Drainge Sluice no.-1 under polder-48 Construction work has been completed 63%. Photo was taken 07.02.2019
Drainge Sluice no.-3/2 under polder-48 Construction work has been completed 58%. Photo was taken 07.02.2019
Drainge Sluice no.-3/2 under polder-48 Construction work has been completed 58%. Photo was taken 07.02.2019
Flushing Sluice no. 1 under polder-48 Construction Work has been completed 41 %. Photo was taken 07.02.2019
Flushing Sluice no. 1 under polder-48 Construction Work has been completed 41 %. Photo was taken 07.02.2019
Drainge Sluice no.-3/4 A under polder-48 Construction work has been completed 58%. Photo was taken 07.02.2019
Drainge Sluice no.-3/4 A under polder-48 Construction work has been completed 58%. Photo was taken 07.02.2019
Flushing Sluice no. 4 under polder-48 Construction Work has been completed 84 %. Photo was taken 07.02.2019
Flushing Sluice no. 4 under polder-48 Construction Work has been completed 84 %. Photo was taken 07.02.2019
DS-1 under construction (progress 3%).This photo was taken on 25.11.2018.
Meeting with FE & CECO manager.This photo was taken on 25.11.2018.
CC blocks manufactured at Alipur Casting Yard under polder-48. Per day CC block production rate is 350 numbers.This photo was taken on 24.07.2018
CC blocks manufactured at Alipur Casting Yard under polder-48. Per day CC block production rate is 350 numbers.This photo was taken on 24.07.2018
CC blocks manufactured at Alipur Casting Yard under polder-48. Per day CC block production rate is 350 numbers.This photo was taken on 24.07.2018
Flushing Sluice no.- 04 under polder- 48. Construction Work has been completed about 90%. Remaining gate and CC block setting .This photo was taken on 24.07.2018
Flushing Sluice no.- 04 under polder- 48. Construction Work has been completed about 90%. Remaining gate and CC block setting .This photo was taken on 24.07.2018
Flushing Sluice no.- 04 under polder- 48. Construction Work has been completed about 90%. Remaining gate and CC block setting .This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018
Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018