PROJECT PROGRESS PHOTO DOCUMENTATION & PHTOGRAPHY

Drainage Sluice

Drainage Sluice no.-10 under polder-32 Construction work has been completed 77%. Photo was taken 04.03.2019

Drainage Sluice

Drainage Sluice no.-11 under polder-32 Construction work has been completed 30%. Photo was taken 04.03.2019

Flushing Sluice

Flushing Sluice no.-10 under polder-32 Construction work has been completed 12 %. Photo was taken 04.03.2019

Embankment work

Embankment work from chainage KM 1+750 to KM 2+750 under polder -32 . Re-SectioningWork is on going. Photo was taken 04.03.2019

Embankment work

Embankment work from chainage KM 21+000 to KM 21+300 under polder -32 . Re-SectioningWork is on going. Photo was taken 04.03.2019

Nalian Closure Dam

The workers filled soil in synthetic sacks and raising the boat for dumping the Nalian Closure Dam. Photo was taken 04.03.2019

Nalian Closure Dam

The workers filled soil in synthetic sacks and raising the boat for dumping the Nalian Closure Dam. Photo was taken 04.03.2019

 CC Block

" Water is spraying in CC Block at Pankhali CC Block manufacturing plant no. 01 under polder-32.This photo was taken on 27.11.2018."

 CC Block

Storge CC Block at Pankhali CC Block manufacturing plant no. 01 under polder-32.This photo was taken on 27.11.2018.                   

Joynagor Bazar

"Received compensation from BWDB but yet to remove their structures from the alignment of embankment chainage: From 11+500 to 11+900 under polder-32.This photo was taken on 27.11.2018."

Joynagor Bazar

"Received compensation from BWDB but yet to remove their structures from the alignment of embankment chainage: From 11+500 to 11+900 under polder-32.This photo was taken on 27.11.2018."

Drainage Sluice

Drainage Sluice no. 11 under polder-32 Construction Work has been completed 3%.This photo was taken on 27.11.2018.                        

Drainage Sluice

Drainage Sluice no. 11 under polder-32 Construction Work has been completed 3%.This photo was taken on 27.11.2018.

Drainage Sluice

Drainage Sluice no. 10 under polder-32 Construction Work has been completed 30%.This photo was taken on 27.11.2018.

Drainage Sluice

Drainage Sluice no. 10 under polder-32 Construction Work has been completed 30%.This photo was taken on 27.11.2018.

 Nalian Closuer Dam

Sand filled synthetic bag dumping is going on in Nalian Closuer Dam under polder-32.This photo was taken on 27.11.2018.

 Nalian Closuer Dam

Sand filled synthetic bag dumping is going on in Nalian Closuer Dam under polder-32.This photo was taken on 27.11.2018.

 Nalian Closuer Dam

Sand filled synthetic bag dumping is going on in Nalian Closuer Dam under polder-32.This photo was taken on 27.11.2018.

Drainage Sluice

Drainage Sluice no. 01 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Drainage Sluice

Drainage Sluice no. 01 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Drainage Sluice

Drainage Sluice no. 16 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Drainage Sluice

Drainage Sluice no. 16 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Embankment Work

Embankment work from chainage km 10+200 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Embankment Work

Embankment work from chainage km 10+200 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Embankment Work

Embankment work from chainage km 11+000 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Embankment Work

mbankment work from chainage km 11+100 under polder-35/1. Only tarfing and crest work has been remained.This photo was taken on 4 July 2018.

Embankment Work

Embankment work from chainage km 11+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Embankment Work

Embankment work from chainage km 11+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Embankment Work

Embankment work from chainage km 11+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Embankment Work

Embankment work from chainage km 19+000 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Embankment Work

Embankment work from chainage km 19+000 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Emergency Work

Emergency work from chainage KM 16+135 under polder-32.This photo was taken on 4 July 2018.

Emergency Work

Emergency work from chainage KM 16+135 under polder-32.This photo was taken on 4 July 2018.

Emergency Work

Emergency work from chainage KM 16+135 under polder-32.This photo was taken on 4 July 2018.

Emergency Work

Emergency work from chainage KM 16+135 under polder-32.This photo was taken on 4 July 2018.

Slope Protection Work

Slope protection work from chainage KM 9+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Slope Protection Work

Slope protection work from chainage KM 9+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Slope Protection Work

Slope protection work from chainage KM 9+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Slope Protection Work

Slope protection work from chainage KM 9+500 under polder-32 Construction Work has been completed fully.This photo was taken on 4 July 2018.

Embankment Works

Earth/Embankment work of polder-32. Slop protection with tarfing work is being continued of chainage: 24+500 KM (Date: 30/05/2018)

Drainage Sluice -01

Construction work is being constructed of Drainage Sluice no.01 under polder-32. (Date: 05/04/2018)

Drainage Sluice -02

Drainage Sluice no. 02 under polder-32 construction Work has been completed about 90%. Connecting canal not yet to be done. (Date:05/04/2018)

Drainage Sluice -02

Drainage Sluice no. 02 under polder-32 construction Work has been completed about 90%. Connecting canal not yet to be done. (Date:05/04/2018)

River bank protection

Construction work is being constructed of Drainage Sluice no.01 under polder-32. (Date: 05/04/2018)

River bank protection

Construction work is being constructed of Drainage Sluice no.01 under polder-32. (Date: 05/04/2018)

Drainage Sluice

"Drainage Sluice No. - 11. Work Status: In Operation. Date of Image: 27/06/19 "

Embankment work

"Embankment work in embargo condition due to LAP/RAP issue. Chainage: Km 0-0.468. Date of Image: 27/06/19 "

Embankment work

"Embankment work in embargo condition due to LAP/RAP issue. Chainage: Km 0-0.468. Date of Image: 27/06/19 "

Embankment work

"Embankment work in embargo condition due to LAP/RAP issue. Chainage: Km 0-0.468. Date of Image: 27/06/19 "

Drainage Sluice

"Drainage Sluice No. - 10. Work Status: 93%. Date of Image: 27/06/19 "

Drainage Sluice

"Drainage Sluice No. - 09. Work Status: In Operation. Date of Image: 27/06/19 "

Embankment work

"Embankment work dropped because this road is under LGED. Chainage: Km 39.792-41.7. Date of Image: 27/06/19 "

Embankment Work

" Dumping of Geo Bag ongoing in damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019"

Embankment Work

"Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019 "

Embankment Work

" Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019"

Embankment Work

" Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019"

Drainage Sluice

"Drainage Sluice no.-6 under polder-33 Construction work has been completed 24%. Photo was taken 06.03.2019"

Flushing inlets

"Flushing inlets no. -5 under polder-33 Construction work has been completed 58%. Photo was taken 06.03.2019"

Flushing inlets

"Flushing inlets no. -6 under polder-33 Construction work has been completed 63%. Photo was taken 06.03.2019"

Flushing inlets

"Flushing inlets no. -6 under polder-33 Construction work has been completed 23%. Photo was taken 06.03.2019"

Embankment work

"For Embankment work market is re-located from chainage km 0+00 to Km 0+500 under polder-33. Photo was taken 06.03.2019"

Embankment work

"Embankment work ( Re-Sectioning is ongoing) from chainage km 0+957 to Km 1+188 under polder-33 . Photo was taken 06.03.2019"

Slope Protection Work

"Slope Protection Work from chainage km 0+800 to 1+200 under polder-33. Work has been completed. Photo was taken 06.03.2019"

Drainage Sluice

Drainage Sluice no. 08 under polder-33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Embankment work

Embankment work from chainage km 28+510 - km 29+430 under polder-33 Construction Work has been completed fully in this section.This photo was taken on 3 July 2018.

Khal/Canal Excavation/Re-excavation Work

Khal/Canal Excavation/Re-excavation work from chainage km 3+150 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Khal/Canal Excavation/Re-excavation Work

Khal/Canal Excavation/Re-excavation work from chainage km 3+150 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Khal/Canal Excavation/Re-excavation Work

Khal/Canal Excavation/Re-excavation work from chainage km 3+150 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Khal/Canal Excavation/Re-excavation Work

Khal/Canal Excavation/Re-excavation work from chainage km 3+150 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Khal/Canal Excavation/Re-excavation Work

Khal/Canal Excavation/Re-excavation work from chainage km 3+500 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Khal/Canal Excavation/Re-excavation Work

Khal/Canal Excavation/Re-excavation work from chainage km 3+500 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Khal/Canal Excavation/Re-excavation Work

Khal/Canal Excavation/Re-excavation work from chainage km 3+500 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

KBank Protection Work

Bank Protection work from chainage KM 21+500 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Bank Protection work

Bank Protection work from chainage KM 21+500 under polder -33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Drainage Sluice

Drainage Sluice no. 11 under polder-33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Embankment Work

Embankment work from chainage km 41+500 under polder-33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

Embankment Work

Embankment work from chainage km 41+500 under polder-33 Construction Work has been completed fully.This photo was taken on 3 July 2018.

CC Block

Storage CC Block at Mongla CC Block manufacturing plant under polder-33.This photo was taken on 28.11.2018.

CC Block

Water is spraying in CC Block at Mongla CC Block manufacturing plant under polder-33.This photo was taken on 28.11.2018.

Drainage Sluice

Drainage Sluice no. 10 under polder-33 Construction Work has been completed 0%.This photo was taken on 28.11.2018.

Drainage Sluice

Drainage Sluice no. 10 under polder-33 Construction Work has been completed 0 %.This photo was taken on 28.11.2018.

Flushing Sluice

Flushing Sluice no. 15 under polder-33 Construction Work has been completed 0 %.This photo was taken on 28.11.2018.

Flushing Sluice

Flushing Sluice no. 15 under polder-33 Construction Work has been completed 0 %.This photo was taken on 28.11.2018.

Flushing Sluice

Flushing Sluice no. 05 under polder-33 Construction Work has been completed 1%.This photo was taken on 28.11.2018.

Flushing Sluice

Flushing Sluice no. 05 under polder-33 Construction Work has been completed 1%.This photo was taken on 28.11.2018.

Flushing Sluice

Flushing Sluice no. 06 under polder-33 Construction Work has been completed 3%.This photo was taken on 28.11.2018.

Flushing Sluice

Flushing Sluice no. 06 under polder-33 Construction Work has been completed 3%.This photo was taken on 28.11.2018.

Drainage Sluice

Drainage Sluice no. 10 under polder-33 Construction Work has been completed 3%.This photo was taken on 28.11.2018.

Drainage Sluice

Drainage Sluice no. 10 under polder-33 Construction Work has been completed 3%.This photo was taken on 28.11.2018.

Slope protection work

"Slope protection work from chainage from KM 43+700 to 43+840 under polder-33 Construction Work has been completed 70%.This photo was taken on 28.11.2018."

Slope protection work

"Slope protection work from chainage from KM 43+700 to 43+840 under polder-33 Construction Work has been completed 70%.This photo was taken on 28.11.2018."

Embankment Work

"Received compensation from BWDB but yet to remove their structures from the alignment of embankment chainage: From 43+500 to 44+000 under polder-33.This photo was taken on 28.11.2018."

Khal re-excavation

Dhopadi Khal(chainage 0+000 to 4+073 km) re-excavation works is being continued at polder-33. (Date: 30/05/2018)

Khal re-excavation

Dhopadi Khal(chainage 0+000 to 4+073 km) re-excavation works is being continued at polder-33. (Date: 30/05/2018)

Drainage Sluice-09

Drainage Sluice no. 09 under polder-33 construction Work has been completed about 90%. Connecting canal not yet to be done. (Date: 30/05/2018)

Drainage Sluice-09

Drainage Sluice no. 09 under polder-33 construction Work has been completed about 90%. Connecting canal not yet to be done. (Date: 30/05/2018)

Drainage Sluice -07

Construction work is being constructed of Drainage Sluice no. 07 under polder-33. (Date:30/05/2018)

Flushing Sluice

Flushing Sluice No. - 22. Work Status: 96%. Date of Image: 28/06/19

Embankment work

Embankment work. Work Status: 95%. Date of Image: 28/06/19

Embankment work

Embankment work (CC Block dumping ongoing). Work Status: 80%. Date of Image: 28/06/19

Embankment work

Embankment work (CC Block dumping ongoing). Work Status: 80%. Date of Image: 28/06/19

Drainage Sluice

Drainage Sluice No. - 04. Work Status: 100%. Date of Image: 28/06/19

Embankment work

Embankment work (Some existing houses and trees). Date of Image: 28/06/19

Embankment work

Embankment work (Some existing houses and trees). Date of Image: 28/06/19

Emabankment Work

Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

Damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

Emergency ring bundh work ongoing in damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

Emergency ring bundh work ongoing in damaged area of embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

New crack on embankment due to Cyclone "Fani". Photo was taken on 07.05.2019

Emabankment Work

PD was discussing with local people about the new allignment of embankment. Photo was taken on 07.05.2019

Emabankment Work

PD was discussing with local people about the new allignment of embankment. Photo was taken on 07.05.2019

Emabankment Work

PD was discussing with local people about the new allignment of embankment. Photo was taken on 07.05.2019

CC Block

Tafalbari CC Block Manufacturing plant. Photo was taken on 07.05.2019

Drainage Sluice -04

Construction work is being constructed of Drainage Sluice no.04 under polder-35/1. (Date:27/05/2018)

Flushing Sluice

Flushing Sluice no. 17 under polder-35/1 Construction Work has been completed about 90%. Connecting canal not yet to be done. This photo was taken on 2 July 2018.

Drainage Sluice

Drainage Sluice no. 17 under polder-35/1 Construction Work has been completed about 90%. Connecting canal not yet to be done.This photo was taken on 2 July 2018.

Embankment Work

Embankment work from chainage km 39+000 under polder-35/1. Crest work and turfing is remained in this section.This photo was taken on 2 July 2018.

Embankment Work

Embankment work from chainage km 39+000 under polder-35/1. Crest work and turfing is remained in this section.This photo was taken on 2 July 2018.

Embankment Work

Embankment work from chainage km 51+500 under polder-35/1. Crest work and turfing is remained in this section.This photo was taken on 2 July 2018.

Embankment Work

Embankment work from chainage km 51+500 under polder-35/1. Work not yet started.This photo was taken on 2 July 2018.

Drainage Sluice

Drainage Sluice no. 17 under polder-35/1 Construction Work has been completed about 90%. Connecting canal not yet to be done.This photo was taken on 2 July 2018.

Drainage Sluice

Drainage Sluice no. 17 under polder-35/1 Construction Work has been completed about 90%. Connecting canal not yet to be done.This photo was taken on 2 July 2018.

Flushing inlets

"Flushing inlets no. -14 under polder-35/3 Construction work has been completed 78%. Photo was taken 07.03.2019"

Flushing Sluice

Flushing Sluice no. 18 under polder-35/1 Construction Work has been completed 5%. . This photo was taken on 25.11.2018.

Flushing Sluice

Flushing Sluice no. 18 under polder-35/1 Construction Work has been completed 5%. . This photo was taken on 25.11.2018.

Flushing Sluice

Flushing Sluice no. 19 under polder-35/1 Construction Work has been completed 4%. This photo was taken on 25.11.2018.

Flushing Sluice

Flushing Sluice no. 19 under polder-35/1 Construction Work has been completed 4%. This photo was taken on 25.11.2018.

Drainage Sluice

Drainage Sluice no. 14 under polder-35/1 Construction Work has been completed 1%.This photo was taken on 25.11.2018.

Drainage Sluice

Drainage Sluice no. 15 under polder-35/1 Construction Work has been completed 2%.This photo was taken on 25.11.2018.

CC Block

Water is spraying in CC Block at tafalbari CC Block manufacturing plant under polder-35/1.This photo was taken on 25.11.2018.

CC Block

Storge CC Block at tafalbari CC Block manufacturing plant under polder-35/1.This photo was taken on 25.11.2018.

CC Block

The plastic piece found in the prepared CC Block are being canceled

CC Block

Workers are neting brick chips using without PPE.This photo was taken on 25.11.2018.

CC Block

Water is spraying in CC Block at Daratana CC Block manufacturing plant under polder-35/3.This photo was taken on 29.11.2018.

CC Block

Storage CC Block at Daratana CC Block manufacturing plant under polder-35/3.This photo was taken on 29.11.2018.

Flushing Sluice

Flushing Sluice no. 05 under polder-35/3 Construction Work has been completed 23%.This photo was taken on 29.11.2018.

Flushing Sluice

Flushing Sluice no. 14 under polder-35/3 Construction Work has been completed 8%.This photo was taken on 29.11.2018.

 Mosque

"There is a Mosque situated in the chainage: From km 14+000 to km 14+500 in Radhaballov under polder-35/3.This photo was taken on 29.11.2018."

Cemeterie

"There is a Cemeterie situated in the chainage: From km 14+000 to km 14+500 in Radhaballov under polder-35/3.This photo was taken on 29.11.2018."

Electric Pole

"Many Electric Pole situated in the chainage: From km 14+000 to km 14+500 in Radhaballov under polder-35/3.This photo was taken on 29.11.2018."

House

"There are still one house in the chainage: From km 30+000 to km 30+500 in Khegraghat under polder-35/3.This photo was taken on 29.11.2018."

Earth/Embankment Work

Earth/Embankment work of polder 35/3 has been completed from chainage : 16+892 to 19+620 . (Date:27/05/2018)

Drainage Sluice -01

Construction work is being constructed of Drainage Sluice no.01 under polder-35/3. (Date:28/05/2018)

Drainage Sluice

Drainage Sluice no. 1 under polder-35/3 . The structure was under construction and work progress is 77.7 %.This photo was taken on 5 July 2018.

Drainage Sluice

Drainage Sluice no. 1 under polder-35/3 . The structure was under construction and work progress is 77.7 %.This photo was taken on 5 July 2018.

Drainage Sluice

Drainage Sluice no. 1 under polder-35/3 . The structure was under construction and work progress is 77.7 %.This photo was taken on 5 July 2018.

Drainage Sluice

Drainage Sluice no. 4 under polder-35/3 . The structure was under construction and work progress is 69 %.This photo was taken on 5 July 2018.

Drainage Sluice

Drainage Sluice no. 4 under polder-35/3 . The structure was under construction and work progress is 69 %.This photo was taken on 5 July 2018.

Drainage Sluice

Drainage Sluice no. 4 under polder-35/3 . The structure was under construction and work progress is 69 %.This photo was taken on 5 July 2018.

Drainage Sluice

Old Drainage Sluice.This photo was taken on 5 July 2018.

Drainage Sluice

Old Drainage Sluice.This photo was taken on 5 July 2018.

Flushing Sluice

Flushing Sluice no. 13 under polder-35/3 Construction Work has been completed 100 %.This photo was taken on 5 July 2018.

Flushing Sluice

Flushing Sluice no. 14 under polder-35/3 Construction Work has been completed 74 %.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 4+500 under polder-35/3.Crest work and turfing is remained in this section.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 4+500 under polder-35/3.Crest work and turfing is remained in this section.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 5+500 under polder-35/3. Crest work and turfing is remained in this section.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 5+500 under polder-35/3. Crest work and turfing is remained in this section.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 6+200 under polder-35/3 Construction Work has been completed fully.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 6+500 under polder-35/3 Construction Work has been completed fully.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 7+500 under polder-35/3 Construction Work has been completed fully.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 7+500 under polder-35/3 Construction Work has been completed fully.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 7+500 under polder-35/3 Construction Work has been completed fully.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 9+000 under polder-35/3 Work in progress.This photo was taken on 5 July 2018.

Embankment Work

Embankment work from chainage km 9+000 under polder-35/3 Work in progress.This photo was taken on 5 July 2018.

 CC Block

Nadmulla CC Block Manufacturing plant. Per day CC Blocks production on an average-9500. Photo was taken 23.04.2019

River Bank Protection Work

River Bank Protection Work from chainage km 51.50 to km 54.00 under polder-39/2C. Dumping is on going. Photo was taken 23.04.2019

River Bank Protection Work

River Bank Protection Work from chainage km 51.50 to km 54.00 under polder-39/2C. CC Block placing only 600 m . Photo was taken 23.04.2019

River Bank Protection Work

River Bank Protection Work from chainage km 51.50 to km 54.00 under polder-39/2C. CC Block placing only 600 m. Photo was taken 23.04.2019

Drainage Sluice

Drainage Sluice no.-7 under polder-39/2C. Construction work has been completed 42%. Photo was taken 27.03.2019

Drainage Sluice

Drainage Sluice no.-12 under polder-39/2C. Construction work has been completed 84%. Photo was taken 27.03.2019

River Bank Protection Work

River Bank Protection Work from chainage km 51.50 to km 54.00 under polder-39/2C. Dumping is on going. Photo was taken 27.03.2019

Bank Protection Work

Bank Protection work from chainage KM 51+500 to KM54+000 under polder -39/2C . Work is on going. Photo was taken 09.02.2019

Bank Protection Work

Bank Protection work from chainage KM 51+500 to KM54+000 under polder -39/2C . Work is on going. Photo was taken 09.02.2019

Bank Protection Work

Bank Protection work from chainage KM 51+500 to KM54+000 under polder -39/2C . Work is on going. Photo was taken 09.02.2019

CCB field/yard

CC block field.This photo was taken on 27.11.2018.

DS-1

DS-1 under construction (97%).This photo was taken on 27.11.2018.

Drainage Sluice

Drainage Sluice no.-12 under polder -39/2C. Construction work has been completed 70%. Remaining raling and third lift wing wall.This photo was taken on 22.07.2018

Drainage Sluice

Drainage Sluice no.-12 under polder -39/2C. Construction work has been completed 70%. Remaining raling and third lift wing wall.This photo was taken on 22.07.2018

Drainage Sluice

Drainage Sluice no.-12 under polder -39/2C. Construction work has been completed 70%. Remaining raling and third lift wing wall.This photo was taken on 22.07.2018

Drainage Sluice

Drainage Sluice no.-12 under polder -39/2C. Construction work has been completed 70%. Remaining raling and third lift wing wall.This photo was taken on 22.07.2018

Drainage Sluice

Drainage Sluice no.-12 under polder -39/2C. Construction work has been completed 70%. Remaining raling and third lift wing wall.This photo was taken on 22.07.2018

Drainage Sluice

Drainage Sluice no.-2 under polder-40/2. Construction work has been completed 82%. Photo was taken 27.03.2019

Drainage Sluice

Drainage Sluice no.-3 under polder-40/2. Construction work has been completed 12%. Photo was taken 27.03.2019

Drainage Sluice

Drainage Sluice no.-5 under polder-40/2. Construction work has been completed 20%. Photo was taken 27.03.2019

Flushing inlets

Flushing inlets no. -4/1 under polder-40/2. Construction work has been completed 84%. Photo was taken 27.03.2019

Flushing inlets

Flushing inlets no. -9 under polder-40/2. Construction work has been completed 28%. Photo was taken 27.03.2020

 Embankment work

Embankment work from chainage Km 4+150 to km 5.850 under polder -40/2 . Work has been completed. Photo was taken 27.03.2019

 Embankment work

Embankment work from chainage Km 6+800 to km 7+500 under polder -40/2 . Re-Sectioning work is ongoing. Photo was taken 27.03.2019

 Embankment work

Embankment work from chainage Km 9+000 to km 10+500 under polder -40/2 . Re-Sectioning work is ongoing. Photo was taken 27.03.2019

 Embankment work

Embankment work from chainage Km 12+000 to km 12+400 under polder -40/2 . Re-Sectioning work is ongoing. Photo was taken 27.03.2019

 Embankment work

Embankment work from chainage Km 12+000 to km 12+400 under polder -40/2 . Re-Sectioning work is ongoing. Photo was taken 27.03.2019

Flushing inlets

Flushing inlets no. -10 under polder-40/2. Construction work has been completed 58%. Photo was taken 27.03.2019

CC Blocks

Gahorpur CC Blocks Manufacturing Plant . Photo was taken 08.02.2019

CC Blocks

Gahorpur CC Blocks Manufacturing Plant . Photo was taken 08.02.2019

Embankment Work

Embankment work from chainage km 4+150 to Km 6+650 under polder-40/2 work has been fully completed 2.40 km out of 34.40 km. Photo was taken 08.02.2019

Embankment Work

Embankment work from chainage km 4+150 to Km 6+650 under polder-40/2 work has been fully completed 2.40 km out of 34.40 km. Photo was taken 08.02.2019

Flushing Inlets

Flushing inlets no. 4/1 under polder-40/2 Construction work has been completed 84%. Photo was taken 08.02.2019

Drainage Sluice

Drainage Sluice no.-2 under polder-40/2 Construction work has been completed 82%. Photo was taken 08.02.2019

Drainage Sluice

Drainage Sluice no.-2 under polder-40/2 Construction work has been completed 82%. Photo was taken 08.02.2019

Embankment Work

Embankment from chainage km 3+00 to Km 4+100 under polder-40/2 total free land is 11.5 km in different chainage . Photo was taken 08.02.2019

Embankment Work

Embankment from chainage km 3+00 to Km 4+100 under polder-40/2 total free land is 11.5 km in different chainage . Photo was taken 08.02.2019

Embankment Work

Embankment from chainage km 3+00 to Km 4+100 under polder-40/2 total free land is 11.5 km in different chainage . Photo was taken 08.02.2019

Embankment Work

Embankment from chainage km 3+00 to Km 4+100 under polder-40/2 total free land is 11.5 km in different chainage . Photo was taken 08.02.2019

Drainage Sluice

Drainage Sluice no.-4_5 under polder-40/2 Construction work has been completed 6 %. Photo was taken 08.02.2019

Drainage Sluice

Drainage Sluice no.-4_5 under polder-40/2 Construction work has been completed 6 %. Photo was taken 08.02.2019

Flushing Sluice

Flushing Sluice no.-9 under polder-40/2 Construction work has been completed 10 %. Photo was taken 08.02.2019

Flushing Sluice

Flushing Sluice no.-9 under polder-40/2 Construction work has been completed 10 %. Photo was taken 08.02.2019

Flushing Sluice

Flushing Sluice no.-10 under polder-40/2 Construction work has been completed 36 %. Photo was taken 08.02.2019

Flushing Sluice

Flushing Sluice no.-10 under polder-40/2 Construction work has been completed 36 %. Photo was taken 08.02.2019

Flushing Sluice

Flushing Sluice no. -4/1 under polder- 40/2. Construction Work has been completed about 90%. Remaining block placing and fit on gate .This photo was taken on 22.07.2018

Flushing Sluice

Flushing Sluice no. -4/1 under polder- 40/2. Construction Work has been completed about 90%. Remaining block placing and fit on gate .This photo was taken on 22.07.2018

Flushing Sluice

Flushing Sluice no. -4/1 under polder- 40/2. Construction Work has been completed about 90%. Remaining block placing and fit on gate .This photo was taken on 22.07.2018

Flushing Sluice

Flushing Sluice no. -4/1 under polder- 40/2. Construction Work has been completed about 90%. Remaining block placing and fit on gate .This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 4+100 - km 5+855 under polder-40/2. Work has been completed 100%.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 5+950 -Km 6+650 under polder-40/2. Only turfing and crest work has been remained.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 5+950 -Km 6+650 under polder-40/2. Only turfing and crest work has been remained.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 5+950 -Km 6+650 under polder-40/2. Only turfing and crest work has been remained.This photo was taken on 22.07.2018

Embankment Work

Embankment work from chainage km 5+950 -Km 6+650 under polder-40/2. Only turfing and crest work has been remained.This photo was taken on 22.07.2018

CC blocks

CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018

CC blocks

CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018

CC blocks

CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018

CC blocks

CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018

CC blocks

CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018

CC blocks

CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018

CC blocks

CC blocks manufactured at Gahorpur Casting Yard under polder-40/2. Per day CC block production rate is 450 numbers.This photo was taken on 22.07.2018

LAP/RAP

Meeting with LAP/RAP staff.This photo was taken on 26.11.2018.

DS-2

DS-2 under construction (2%).This photo was taken on 26.11.2018.

Flushing Sluice

Flushing Sluice no.-1 under polder-41/1. Construction work has been completed 72%. Photo was taken 25.04.2019

Flushing Sluice

Flushing Sluice no.-3 under polder-41/1. Construction work has been completed 72%. Photo was taken 25.04.2019

Drainage Sluice

Drainage Sluice no.-5 under polder-41/1. Construction work has been completed 72%. Photo was taken 25.04.2019

Drainage Sluice

Drainage Sluice no.-7 under polder-41/1. Construction work has been completed 60%. Photo was taken 25.04.2019

Drainage Sluice

Drainage Sluice no.-1 under polder-41/1. Construction work has been completed 18%. Photo was taken 28.03.2019

Drainage Sluice

Drainage Sluice no.-5 under polder-41/1. Construction work has been completed 69%. Photo was taken 28.03.2019

Drainage Sluice

Drainage Sluice no.-6 under polder-41/1. Construction work has been completed 55%. Photo was taken 28.03.2019

Drainage Sluice

Drainage Sluice no.-7 under polder-41/1. Construction work has been completed 28%. Photo was taken 28.03.2019

Drainage Sluice

Drainage Sluice no.-8 under polder-41/1. Construction work has been completed 70%. Photo was taken 28.03.2019

Drainage Sluice

Drainage Sluice no.-9 under polder-41/1. Construction work has been completed 60%. Photo was taken 28.03.2019

Flushing inlets

Flushing inlets no. -1 under polder-41/1. Construction work has been completed 71%. Photo was taken 28.03.2019

Flushing inlets

Flushing inlets no. -3 under polder-41/1. Construction work has been completed 70%. Photo was taken 28.03.2019

Flushing inlets

Flushing inlets no. -8 under polder-41/1. Construction work has been completed 84%. Photo was taken 28.03.2019

Flushing inlets

Flushing inlets no. -9 under polder-41/1. Construction work has been completed 84%. Photo was taken 28.03.2019

Flushing inlets

Flushing inlets no. -15 under polder-41/1. Construction work has been completed 84%. Photo was taken 28.03.2019

Embankment work

Embankment work from chainage Km 6+100 to km 6+500 under polder -41/1 . Re-Sectioning work is ongoing. Photo was taken 28.03.2019

Embankment work

Embankment work from chainage Km 6+100 to km 6+500 under polder -41/1 . Re-Sectioning work is ongoing. Photo was taken 28.03.2019

Flushing Sluice

Flushing Sluice no.-8 under polder-41/1 Construction work has been completed 84%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-5 under polder-41/1 Construction work has been completed 66%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-5 under polder-41/1 Construction work has been completed 66%. Photo was taken 07.02.2019

Flushing  Sluice

Flushing Sluice no. 9 under polder-41/1 Construction Work has been completed 84%. Photo was taken 07.02.2019

Flushing  Sluice

Flushing Sluice no. 9 under polder-41/1 Construction Work has been completed 84%. Photo was taken 07.02.2019

Embankment work

Embankment work from chainage km 6+100 to KM 13+000 under polder-41/1. Only tarfing and crest work has been remained. Photo was taken 07.02.2019

Embankment work

Embankment work from chainage km 6+100 to KM 13+000 under polder-41/1. Only tarfing and crest work has been remained. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-7 under polder-41/1 Construction work has been completed 12%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-7 under polder-41/1 Construction work has been completed 12%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-8 under polder-41/1 Construction work has been completed 66%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-8 under polder-41/1 Construction work has been completed 66%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-6 under polder-41/1 Construction work has been completed 28%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-6 under polder-41/1 Construction work has been completed 28%. Photo was taken 07.02.2019

Flushing  Sluice

Flushing Sluice no. 15 under polder-41/1 Construction Work has been completed 84%. Photo was taken 07.02.2020

Flushing  Sluice

Flushing Sluice no. 15 under polder-41/1 Construction Work has been completed 84%. Photo was taken 07.02.2020

CC Blocks

Gulbonia CC Blocks Manufacturing Plant under polder-41/1 . Photo was taken 07.02.2019

CC Blocks

Gulbonia CC Blocks Manufacturing Plant under polder-41/1 . Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-9 under polder-41/1 Construction work has been completed 44%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-9 under polder-41/1 Construction work has been completed 44%. Photo was taken 07.02.2019

CSE office

Progress Meeting with CSE.This photo was taken on 26.11.2018.

Flushing Sluice

FS-3 under construction (2%).This photo was taken on 26.11.2018.

CC blocks

CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018

CC blocks

CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018

CC blocks

CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018

CC blocks

CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018

CC blocks

CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018

CC blocks

CC blocks manufactured at Burirchar Casting Yard under polder-41/1. Per day CC block production rate is 250 numbers.This photo was taken on 23.07.2018

CC blocks

CC blocks manufactured at Gulbonia Casting Yard under polder-41/1. Per day CC block production rate is 250+ numbers.This photo was taken on 23.07.2018

CC blocks

CC blocks manufactured at Gulbonia Casting Yard under polder-41/1. Per day CC block production rate is 250+ numbers.This photo was taken on 23.07.2018

CC blocks

CC blocks manufactured at Gulbonia Casting Yard under polder-41/1. Per day CC block production rate is 250+ numbers.This photo was taken on 23.07.2018

CC blocks

CC blocks manufactured at Gulbonia Casting Yard under polder-41/1. Per day CC block production rate is 250+ numbers.This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 08 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 08 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 08 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 08 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 09 under polder- 41/1. Construction Work has been completed about 90%. Remaining raling and block setting .This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 09 under polder- 41/1. Construction Work has been completed about 90%. Remaining raling and block setting .This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 09 under polder- 41/1. Construction Work has been completed about 90%. Remaining raling and block setting .This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 09 under polder- 41/1. Construction Work has been completed about 90%. Remaining raling and block setting .This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 15 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 15 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018

Flushing Sluice

Flushing Sluice no. - 15 under polder- 41/1. Construction Work has been completed about 70%. Remaining raling and third lift wing wall .This photo was taken on 23.07.2018

Emergency work

Emergency work from chainage KM 5+050 - KM 5+225 beside the Burir char CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018

Emergency work

Emergency work from chainage KM 5+050 - KM 5+225 beside the Burir char CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018

Emergency work

Emergency work from chainage KM 5+050 - KM 5+225 beside the Burir char CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018

Emergency work

Emergency work from chainage KM 5+050 - KM 5+225 beside the Burir char CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018

Emergency work

Emergency work from chainage KM 13+650 - KM 13+250 beside the Gulbonia CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018

Emergency work

Emergency work from chainage KM 13+650 - KM 13+250 beside the Gulbonia CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018

Emergency work

Emergency work from chainage KM 13+650 - KM 13+250 beside the Gulbonia CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018

Emergency work

Emergency work from chainage KM 13+650 - KM 13+250 beside the Gulbonia CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018

Emergency work

Emergency work from chainage KM 13+650 - KM 13+250 beside the Gulbonia CC Blocks manufactured casting yard under polder-41/1. The work has not started yet.This photo was taken on 23.07.2018

Drainge Sluice

Drainge Sluice no.-2 under polder-47/2 Construction work has been completed 69%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-2 under polder-47/2 Construction work has been completed 69%. Photo was taken 07.02.2019

Flushing Sluice

Flushing Sluice no.-1 under polder-47/2 Construction work has been completed 30%. Photo was taken 07.02.2019

Flushing Sluice

Flushing Sluice no.-1 under polder-47/2 Construction work has been completed 30%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-1 under polder-47/2 Construction work has been completed 63%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-1 under polder-47/2 Construction work has been completed 63%. Photo was taken 07.02.2019

Embankment Works

Embankment work from chainage km 0+000 to KM 2+000 under polder-47/2. Work has been completed 100%. Photo was taken 07.02.2019

Embankment Works

Embankment work from chainage km 0+000 to KM 2+000 under polder-47/2. Work has been completed 100%. Photo was taken 07.02.2019

Embankment slope protection

Gap of Embankment slope protection.This photo was taken on 25.11.2018.

Flushing Sluice Construction

FS-6 under construction (Progress 98%).This photo was taken on 25.11.2018.

Drainage Sluice Construction

DS-1 under construction (2%).This photo was taken on 25.11.2018.

CC blocks

CC blocks manufactured at Ramjanpur Casting Yard under polder-47/2. Per day CC block production rate is 150 numbers.This photo was taken on 25.07.2018

CC blocks

CC blocks manufactured at Ramjanpur Casting Yard under polder-47/2. Per day CC block production rate is 150 numbers.This photo was taken on 25.07.2018

CC blocks

CC blocks manufactured at Ramjanpur Casting Yard under polder-47/2. Per day CC block production rate is 150 numbers.This photo was taken on 25.07.2018

CC blocks

CC blocks manufactured at Ramjanpur Casting Yard under polder-47/2. Per day CC block production rate is 150 numbers.This photo was taken on 25.07.2018

CC blocks

CC blocks manufactured at Ramjanpur Casting Yard under polder-47/2. Per day CC block production rate is 150 numbers.This photo was taken on 25.07.2018

Emergency work

Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018

Emergency work

Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018

Emergency work

Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018

Emergency work

Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018

Emergency work

Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018

Emergency work

Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018

Emergency work

Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018

Emergency work

Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018

Emergency work

Emergency work from chainage KM 6+300 - KM 6+722 under polder-47/2. Work in progress.This photo was taken on 25.07.2018

Embankment work

Embankment work from chainage km 5+500 - 2+575 under polder-47/2. Construction Work has been completed 100%.This photo was taken on 25.07.2018

Embankment work

Embankment work from chainage km 5+500 - 2+575 under polder-47/2. Construction Work has been completed 100%.This photo was taken on 25.07.2018

Embankment work

Embankment work from chainage km 5+500 - 2+575 under polder-47/2. Construction Work has been completed 100%.This photo was taken on 25.07.2018

Embankment work

Embankment work from chainage km 5+500 - 2+575 under polder-47/2. Construction Work has been completed 100%.This photo was taken on 25.07.2018

Flushing Sluice

Flushing Sluice no. - 6 under polder- 47/2. Construction Work has been completed about 70%. Remaining raling and third lift wing wall.This photo was taken on 25.07.2018

Flushing Sluice

Flushing Sluice no. - 6 under polder- 47/2. Construction Work has been completed about 70%. Remaining raling and third lift wing wall.This photo was taken on 25.07.2018

Flushing Sluice

Flushing Sluice no. - 7 under polder- 47/2. Construction Work has been completed about 70%. Remaining raling and third lift wing wall.This photo was taken on 25.07.2018

Flushing Sluice

Flushing Sluice no. - 7 under polder- 47/2. Construction Work has been completed about 70%. Remaining raling and third lift wing wall.This photo was taken on 25.07.2018

Slope Protection Work

Slope Protection Work from chainage km 34.300 to km 34.550 under polder-48. Embankment work has been completed only CC Block placing has been remain. Photo was taken 24.04.2019

Drainage Sluice

Drainage Sluice no.-1 under polder-48. Construction work has been completed 84%. Photo was taken 24.04.2019

Flushing Sluice

Flushing Sluice no. -1 under polder-48. Construction work has been completed 70%. Photo was taken 24.04.2019

Flushing Sluice

Flushing Sluice no. -3 under polder-48. Construction work has been completed 84%. Photo was taken 24.04.2019

Drainage Sluice

Drainage Sluice no. -3/2 under polder-48. Construction work has been completed 74%. Photo was taken 24.04.2019

Drainage Sluice

Drainage Sluice no. -3/4 under polder-48. Construction work has been completed 84%. Photo was taken 24.04.2019

Drainage Sluice

Drainage Sluice no.-1 under polder-48. Construction work has been completed 74%. Photo was taken 29.03.2019

Flushing inlets

Flushing inlets no. -1 under polder-48. Construction work has been completed 50%. Photo was taken 29.03.2019

Slope Protection Work

Slope Protection Work from chainage km 34+377 to 34+878. Dumping is on going. Photo was taken 07.02.2019

Slope Protection Work

Slope Protection Work from chainage km 34+377 to 34+878. Dumping is on going. Photo was taken 07.02.2019

CC Blocks

CC Blocks Manufacturing yYard No. -4 under-48. Photo was taken 07.02.2019

CC Blocks

CC Blocks Manufacturing yYard No. -4 under-48. Photo was taken 07.02.2019

Flushing Sluice

Flushing Sluice no. 1 under polder-48 Construction Work has been completed 30 %. Photo was taken 07.02.2019

Flushing Sluice

Flushing Sluice no. 1 under polder-48 Construction Work has been completed 30 %. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-1 under polder-48 Construction work has been completed 63%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-1 under polder-48 Construction work has been completed 63%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-3/2 under polder-48 Construction work has been completed 58%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-3/2 under polder-48 Construction work has been completed 58%. Photo was taken 07.02.2019

Flushing Sluice

Flushing Sluice no. 1 under polder-48 Construction Work has been completed 41 %. Photo was taken 07.02.2019

Flushing Sluice

Flushing Sluice no. 1 under polder-48 Construction Work has been completed 41 %. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-3/4 A under polder-48 Construction work has been completed 58%. Photo was taken 07.02.2019

Drainge Sluice

Drainge Sluice no.-3/4 A under polder-48 Construction work has been completed 58%. Photo was taken 07.02.2019

Flushing Sluice

Flushing Sluice no. 4 under polder-48 Construction Work has been completed 84 %. Photo was taken 07.02.2019

Flushing Sluice

Flushing Sluice no. 4 under polder-48 Construction Work has been completed 84 %. Photo was taken 07.02.2019

Drainage Sluice

DS-1 under construction (progress 3%).This photo was taken on 25.11.2018.

China Camp

Meeting with FE & CECO manager.This photo was taken on 25.11.2018.

CC blocks

CC blocks manufactured at Alipur Casting Yard under polder-48. Per day CC block production rate is 350 numbers.This photo was taken on 24.07.2018

CC blocks

CC blocks manufactured at Alipur Casting Yard under polder-48. Per day CC block production rate is 350 numbers.This photo was taken on 24.07.2018

CC blocks

CC blocks manufactured at Alipur Casting Yard under polder-48. Per day CC block production rate is 350 numbers.This photo was taken on 24.07.2018

Flushing Sluice

Flushing Sluice no.- 04 under polder- 48. Construction Work has been completed about 90%. Remaining gate and CC block setting .This photo was taken on 24.07.2018

Flushing Sluice

Flushing Sluice no.- 04 under polder- 48. Construction Work has been completed about 90%. Remaining gate and CC block setting .This photo was taken on 24.07.2018

Flushing Sluice

Flushing Sluice no.- 04 under polder- 48. Construction Work has been completed about 90%. Remaining gate and CC block setting .This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018

Slope protection work

Slope protection work from chainage KM 30+670 - KM 34+710 at kuakataSea beach under polder-48. The work has not started yet.This photo was taken on 24.07.2018