Coastal Embankment Improvement Project - Phase - 1 (CEIP-1)

CEIP-1

Contractor

Sl. No. Name of Contractors Package No/Contract No Description of Works Contract Signing Date Time of Completion
01 The First Engineering Bureau of Henan Water Conservancy CEIP-1/W-01 Rehabilitation / Reconstruction and upgrading of Polder 32,33, 35/1 & 35/3 01 November 2015 30 June 2020
02 Chongqing International Construction Corporation CEIP-1/W-02 Rehabilitation / Reconstruction and upgrading of Polder 39/2C, 40/2, 41/1, 43/2C, 47/2 & 48 08 March 2017 Whole Work-42 Months